2025 
Thursday, July 10, 2025
Asphalt paving officially began this morning on Mink Lake Road!
Please drive with caution—loose gravel and debris may be present, and flying rocks from passing vehicles have already caused at least one windshield replacement. To avoid damage, reduce your speed and increase following distance.
Thank you for your patience as we work to improve local infrastructure!
July 2, 2025 - Revitalization of Mink Lake Road
PLEASE NOTE:  Road Paving on Mink Lake Road, part of the Capital Construction Project, is set to begin ahead of schedule on:​​​​​​​
July 7th, 2025, as early as 6:00 a.m.
Continue to expect short-term delays and traffic interruptions during the scheduled work period. Please be sure to continue to exercise caution because of construction when travelling on Mink Lake Road.
The expected completion date and time for paving will be communicated once work is underway and more information becomes available.
Update - Revitalization of Mink Lake Road
PLEASE NOTE:
Gravel Application on Mink Lake Road, part of the Capital Construction Project, is set to begin on
June 23, 2025, as early as 6:00 a.m.
Short-term delays and traffic interruptions are expected to continue during the scheduled work period. Please continue to exercise caution when travelling on Mink Lake Road during the work period.

Gravel Application is tentatively planned to be completed by June 27 at 4:00 p.m.

Please expect delays for the remainder of the construction season.
For more information and a map of the affected area, please visit:
June 4 - Mink Lake Road Construction Update
June 04, 2025
Mink Lake Road Construction Update
PLEASE NOTE:
Culvert replacements on Mink Lake Road, part of the Capital Construction Project, are now complete, and the road is fully open to traffic.

However, short-term delays and traffic interruptions will continue due to ditching operations between Highway 127 and Dam Road.

Pulverization of Mink Lake Road is scheduled to begin as early as
Tuesday, June 10, 2025, at 7:00 a.m.

Please expect delays for the remainder of the construction season.

For updates, please visit:

https://www.hastingshighlands.ca/living-here/roads/construction-road-work-and-closures/ 
Work will take place from Highway 127 to Dam Road, extending roughly 9.1 km. Culvert Replacement work will begin on Mink Lake Road, starting with temporary closures on:
May 27 2025 from 7:00a.m. to 7:00p.m.
May 28 2025 from 7:00a.m. to 1:00p.m.
May 29 2025 from 7:00a.m. to 7:00p.m.
May 30 2025 from 7:00a.m. to 1:00p.m.
June 3 2025 from 7:00a.m. to 7:00p.m.
For more information and a map of the affected area, please visit:

Emergency Access:
We have coordinated with all emergency services to ensure uninterrupted emergency response. Fire trucks will be staged on the Mink Lake side of the closures as a precautionary measure.

Future Work:
There will be additional short-term closures along Mink Lake Road in the coming weeks, as more culverts are installed in preparation for full road rehabilitation. Ditching operations will also be performed along various sections of Mink Lake Road, which may cause temporary delays. 
The 2025 Spring Newsletter was sent out to members of the MLPOA on May 14, 2025
MLPOA - Annual General Meeting
Saturday, August 30, 2025 @ 10:00 am
5 Boulter Lake Road, Lake St. Peter, Ontario.
Saturday, August 2, 2025
3rd Annual MLPOA Member Appreciation BBQ
Location: 1261 Mink Lake Road
2024 Events
SAVE THE DATE - 2024 Activities
**********************************************************************************************************
Saturday, August 3, 2024
2nd Annual MLPOA Member Appreciation BBQ
Location: 1261 Mink Lake Road
************************************************************************************************************
Saturday, August 31, 2024
2024 Mink Lake Property Owners Association Annual General Meeting (AGM)
Location: Lake St. Peter Community Centre
5 Boulter Lake Road, Lake Saint Peter, Ontario. K0L 2K0
Back to Top